What this project is
The main house plus the ADU come to just over 1,200 square feet, of which the ADU itself is 715 square feet, converted from the original garage. A garage conversion is not a new door on an old box: every material inside and out was replaced. At the time of filming the drywall, roof and exterior walls were underway.
Exterior: three coats, two weeks
Stucco goes on in three coats with curing in between: about two days for the first, seven days of curing, then about two days for the last, roughly two weeks in all. That waiting time cannot be skipped. Compress the three coats into a few days and the stucco cracks, and it will not be watertight.
Drywall: 5/8 inch, not 1/2 inch
This project uses 5/8 inch drywall throughout, thicker than the common 1/2 inch, and better against fire, water and moisture. Fire separation matters particularly when a garage becomes living space, so this is not a place to save.
Insulation: R30 roof, R13 walls
The roof is where most heat enters in summer and escapes in winter, so the rating goes up to R30 there, with R13 in the side walls. Insulation is also a sound barrier, which decides how quiet it is between a backyard ADU and the main house.
Structure: an anchor bolt every 4 feet
Seismic anchor bolts go in strictly every 4 feet, tying the wall structure back into the foundation. In an earthquake the front wall does not come down as a sheet. The spacing comes from structural calculation, not judgement on the day.
Details: glass and pipe diameter
Bathroom glass has to be tempered and frosted at the same time: tempered for safety, so it crumbles rather than shatters into shards, and frosted because the city requires it for privacy. The city requires a 3.5 inch toilet drain; this project uses 4 inch, because the larger diameter is less likely to block over the years.
A note on progress: at the time of filming this project was in drywall, roof and exterior wall work, and is not finished. We do not announce delivery dates in advance. Every milestone is tied to the city's own inspection record, and this page will be updated when the project completes.
Common questions
What people ask about this project
Can a garage be converted into an ADU?
Yes. This Arcadia project converted an existing garage into a 715 square foot ADU. A conversion is not just a new door: every material inside and out was replaced, including exterior walls, roof, drywall, insulation, plumbing, electrical and structural reinforcement. Whether you can convert, and how large, depends on your city's rules and the site itself.
Why does exterior stucco take three coats and about two weeks?
Stucco goes on in three coats with curing time in between: roughly two days for the first, seven days of curing, then about two days for the last, so around two weeks in total. That waiting time cannot be skipped. Compressing three coats into a few days causes the stucco to crack and it will not be watertight.
Why use 5/8 inch drywall instead of 1/2 inch?
This project uses 5/8 inch drywall throughout, thicker than the common 1/2 inch. The thicker board performs better against fire, water and moisture. Fire separation matters particularly when a garage becomes living space, so this is not a place to save.
What insulation rating should an ADU have?
This project uses R30 insulation in the roof and R13 in the side walls. The roof is where most heat enters in summer and escapes in winter, so the rating goes higher there. Insulation also works as a sound barrier, which directly affects how quiet things are between a backyard ADU and the main house.
How closely spaced do seismic anchor bolts need to be?
This project places a seismic anchor bolt strictly every 4 feet. The bolts tie the wall structure back into the foundation so that in an earthquake the front wall does not come down as a sheet. The spacing comes from structural calculation, not judgement on the day, and we build to the drawing rather than easing it.
Why does bathroom glass need to be both tempered and frosted?
Two reasons. Tempering is a safety requirement: if the glass breaks it crumbles into small pieces rather than sharp shards. Frosting is the city's privacy requirement for bathrooms. Both have to be satisfied, not one or the other.
What size drain line should a toilet have?
The city requires 3.5 inch. This project uses 4 inch. The larger diameter is there so it is less likely to block over the years. The extra cost is small, and the difference once people are living there is real.
How much does an ADU cost in the San Gabriel Valley, and how long does it take?
Poly Construction builds the structural shell complete from $150 per square foot of floor area, covering foundation, framing, roof, exterior walls, windows and doors, and the plumbing, electrical and HVAC rough-in. Structural shell completion takes 50 business days, with weekends and public holidays not counted. Interior finishes (flooring, cabinets, paint, fixtures) are contracted separately by the owner and are not in that price or timeline.