What happened that day
The whole slab was poured inside one day. At the start of it the rebar was tied, the forms were set and the plumbing and electrical stub-ups were positioned to the drawings and fixed. By the end of it the slab was finished and ready to cure. The video compresses that day into 71 seconds without reordering anything.
Why we are on site for the whole pour
This ADU will offer plenty of later chances to change course. Wall positions can be discussed, the kitchen can be swapped, the flooring can be redone. The foundation offers none: the concrete sets once, and the stub-up positions set with it. Changing them means cutting the slab open, at real cost and real risk. So this is not a day we leave to the crew alone.
The pump truck, because a back yard leaves no other option
A mixer truck cannot get into a back yard, and wheeling a slab's worth of concrete from the front one barrow at a time is not realistic. The pump truck parks at the kerb and sends the concrete through a line over the house and into the forms at the back. Those thick hoses at the start of the video are the pump line.
Spreading, screeding, floating and trowelling
Placed concrete is spread, then screeded to the correct height, and that pass is what decides whether the slab is flat. Floating and trowelling come later, once the concrete has begun to set, closing and compacting the surface. The wait between the two is judged on the state of the concrete, not on the clock.
The pipes standing in the slab
Those are the drain, supply and electrical stub-ups, which later connect to the bathroom, the kitchen and the panel. They are set to the drawings and fixed before the pour, because once the concrete surrounds them nothing moves. Put them in the wrong place and the whole interior layout has to bend around them.
A note on progress: this video is pour day and the project is not finished. We do not announce delivery dates in advance, and every milestone is governed by the city's own inspection record. To protect the owner's privacy we name the city only, never the project address.
Common questions
What people ask about foundations
How long does an ADU foundation take?
The pour itself is one day. On this Rosemead project the slab went from tied rebar to a finished surface inside a single day. The foundation stage as a whole is longer than that one day: before the pour there is excavation, grading, forming, tying rebar, setting the underground plumbing and electrical, and the city rebar inspection; after the pour the concrete has to cure and reach strength before framing starts. The actual number of days depends on the site and on how quickly your city schedules inspections, and we go through that for your specific property at the evaluation.
Can a foundation be changed after it is poured?
Essentially no. Walls can be moved, a kitchen can be swapped, flooring can be redone, but a concrete slab is fixed once it is poured, and so are the positions of the plumbing and electrical stub-ups inside it. Changing them means cutting the slab open, which is expensive and carries real risk. This is the one part of an ADU you cannot correct later, which is why we are on site for the whole pour.
What are plumbing stub-ups and why are they set before the pour?
Stub-ups are the drain, supply and electrical lines that come up out of the slab and later connect to the bathroom, the kitchen and the panel. They have to be positioned to the drawings and fixed in place before the pour, because once the concrete surrounds them their position is permanent. The pipes standing up out of the slab in the video are the stub-ups. If they are in the wrong place, the entire interior layout has to bend around them.
Why use a pump truck instead of pouring straight from the mixer?
A backyard ADU usually leaves no other option. A mixer truck cannot get into a back yard, and wheeling concrete from the front one barrow at a time is not realistic for a slab. The pump truck parks at the kerb and sends the concrete through a line over the house and into the forms at the back. That is how this Rosemead slab was placed.
What is the difference between screeding and the float and trowel finish?
Screeding pulls the freshly placed concrete to the correct height so the slab is flat. Floating and trowelling happen later, once the concrete has begun to set, and close and compact the surface. They are two separate operations at two different moments, with a wait in between while the concrete reaches the right state. Both are visible in the video.
Is pour day noisy, and will it affect the neighbours?
There is noise, mostly from the pump truck and the placement. It is concentrated into one day rather than dragging on. Before we start we agree vehicle access and parking with the owner for that day, and where it makes sense we suggest giving the neighbours advance notice. Each city sets its own permitted working hours and we work inside them.
Does rain affect a concrete pour?
Yes. Rain falling on concrete that has not set damages the surface and affects both strength and flatness, so pour day is decided against the forecast and moved if it has to be. Rescheduling sounds like a delay, but set against pouring a slab with a problem in it, the trade is not a hard one.
What does an ADU cost and how long does it take in the San Gabriel Valley?
Poly Construction builds the structural shell from $150 per square foot of floor area, covering the foundation, structural framing, roof, exterior walls, windows and doors, and the plumbing, electrical and HVAC rough-in. Structural shell completion takes 50 business days, with weekends and public holidays not counted. Interior finishes (flooring, cabinets, paint, fixtures) are contracted by the owner and are not included in that price or that timeline.